208th Street sewer extension and pump station construction
208th Street East Sewer Extension, Solicitation 158837, issued by Pierce County.
At a glance
Pierce County is seeking a contractor to build a new pump station, force main, and gravity sewer system on 208th Street East, including all mechanical, electrical, and civil work. The project has a budget of $9–12 million and must be completed within 308 calendar days from notice to proceed.
Key facts
- Issuing agency
- Pierce County
- Solicitation number
- 158837
- Type
- purchase
- Posted
- Jun 25, 2025
- Response deadline
- Jul 16, 2025, 4:00 PM EDT
- Place of performance
- Pierce County, WA
Official description
Solicitation #2025-MPW-089. Issued by Planning and Public Works. The successful bidder will be responsible for construction of the 208 TH Street Pump Station, force main, and gravity sewer system. The work includes but is not limited to furnishing and installing the pump station wet well, generator, vaults, pumps and associated equipment and controls, electrical panels and cabinets, canopy, power meter, backflow preventer, reinforced concrete pads, asphalt pavement, chain link fence, conduit and wiring, trench dams, various sizes of sewer pipe, concrete manholes, corrosion resistant manholes, and other associated improvements.
The Contractor shall provide all necessary design work, details, calculations and other information required to acquire the Electrical Permit(s) from Tacoma Power and Fire Permits from Pierce County for the proposed Engine/Generator System. The Owner will obtain a Class C Right-of-Way permit from Pierce County for all work in County Right-of-Way. The Contactor shall comply with all conditions of the issued Right-of-Way permit.
The work includes installing and maintaining erosion control BMPs, roadway excavation including removal and disposal of existing pavement and unwanted or excess materials encountered during execution of the project, traffic control, utility coordination, concrete curb ramp and sidewalk restoration, curb ramp installation, roadway restoration, and restoration of disturbed private property. The work also includes design, permitting, construction, operation, maintenance, and removal of temporary construction dewatering systems and sewer bypass systems as necessary to complete the installation of the sanitary sewer improvements.
The work is to be completed within a maximum of three hundred and eight (308) calendar days from the date of the "Notice to Proceed".
The project estimate ra nge is $9,000,000.00 - $12,000,000.00 i ncluding WA State Sales Tax.
Respond to this bid
This solicitation is administered by the issuing agency through its OpenGov procurement portal. The official documents, any addenda and updates, and the procurement officer’s contact information are all posted there, and bid submission happens there, not on SledAtlas.
The direct link to the source posting (documents, addenda, updates, and the procurement contact) is free with a SledAtlas account. Sign in or create a free account.