Chiller replacement general contracting, Ontario County Jail
Re-Bid of Item 1, General Contracting, for the Replacement of the Chiller at Ontario County Jail, Solicitation B25071, issued by Ontario County.
What this job went for
IntelligenceAwarded to Landry Mechanical Contractors, Inc. on Aug 26, 2025.
Bid results · 2 bidders
Every bidder and price, the low bid and the spread:
1 past contract
Who holds it, what it pays and when it ends:
The job
Ontario County is seeking a general contractor to replace the chiller system at the Ontario County Jail. The work involves installing an air-cooled chiller on the roof while maintaining the existing 270T cooling tower and modular chiller system operational during installation, with system cutover scheduled for shoulder months. The project includes demolition and removal of the old cooling tower and chiller.
- Trade
- HVAC
- Also includes
- Roofing; Demolition; Carpentry, drywall, ceilings, casework; Concrete, sidewalk, curb; Painting and coatings
- Kind of work
- Chiller replacement with roof installation
- The work
- Replacement
- Contract
- One job
- Who can bid
- Any qualified firm.
- Issuing agency
- Ontario County
- Solicitation number
- B25071
- Portal id
- 175711
- Type
- purchase
- Posted
- Jun 18, 2025
- Response deadline
- Jul 10, 2025, 3:00 PM EDT
- Questions due
- Jul 1, 2025, 3:00 PM EDT
- Place of performance
- Ontario County, NY
Official posting
Documents, addenda and how to respond are on the agency’s own posting. Open the official posting (free with an account).
Official description
Solicitation #B25071. Issued by Department of Public Works. Ontario County is re-bidding Item 1 (from B25049), the General Contracting portion, of the replacement of its chiller at the Ontario County Jail. This project will need to keep the existing CHW system operational, while the replacement is being installed. Once the new system is installed, the old cooling tower and chiller can be demolished and removed. The existing CHW system consists of a 270T cooling tower and Multi-Stack modular chiller, that are both located in the mechanical room. The replacement system is an air cooled chiller being installed on dunnage on the roof, with heat exchangers located in the mechanical room. The cut over of these systems will need to take place during shoulder months.
Open hvac bids in New York
- OpenDue Nov 19, 2026
- OpenDue Dec 3, 2026
- OpenDue Dec 3, 2026
- OpenDue Dec 16, 2026
- OpenDue Aug 7, 2028
Other trades in New York: RoofingDemolitionCarpentryPick another trade
On the free plan a trade inside a state is your one specific search of the day; a plan searches every trade, every place.